From idea to product, phase by phase

Six phases, separated by gates. Every gate ends in a go, kill, hold or recycle decision, so you always know where you stand. You can bring TDO in at any phase.

  1. G0Phase 0Idea & opportunitySketches, mock-ups
  2. G1Phase 1Concept & feasibilityLooks-like & works-like models
  3. G2Phase 2Detailed design & engineeringAlpha & beta protos
  4. G3Phase 3Tooling & industrialisationFOTS (T0 / T1), dimensional report
  5. G4Phase 4Validation & pilot run0-series, golden sample
  6. G5Phase 5Launch & ramp-upSeries production

G6 · Post-launch review

View the full overview: activities, models and gates per phase
G0 · Idea screeningFits strategy? Worth exploring?
Phase 0

Idea & opportunity

  • Idea capture, user and market insight
  • Competitor scan, first IP check
  • Rough business case and target cost
Sketches, mood boardsPaper and cardboard mock-ups
G1 · Concept approvalBusiness case OK, budget for concept work
Phase 1

Concept & feasibility

  • Product requirements (PRS / PRD)
  • Concept options and selection
  • Technical feasibility, key risks
  • Make-or-buy, early supplier talks
Sketch models (foam, 3D print)Looks-like modelWorks-like proof of principle
G2 · Concept freezeConcept chosen, requirements baselined
Phase 2

Detailed design & engineering

  • 3D CAD, drawings, tolerances
  • DFM / DFA with the toolmaker
  • FMEA, design verification tests
  • Supplier and material selection
Alpha proto (print / CNC)Beta proto (near-production: vacuum cast, soft tool)DVT samples
G3 · Design freeze / tool releaseDesign verified, tooling PO placed
Phase 3

Tooling & industrialisation

  • Tool build (moulds, dies)
  • Process and assembly line design
  • Fixtures, test jigs, control plan
  • Tool correction loop
FOTS (T0 / T1 shots)T2…Tn corrected samplesDimensional report / FAI
G4 · Tool & sample approvalFOTS in spec, OTS / PPAP signed off
Phase 4

Validation & pilot run

  • Production validation (PVT)
  • Certification (CE, UL, etc.)
  • Packaging, manuals, service parts
  • Line validation, yield and cycle time
0-series / pilot seriesCertification samplesGolden sample
G5 · Production release (SOP)Quality, cost and capacity confirmed
Phase 5

Launch & ramp-up

  • Ramp-up to rate
  • Field feedback, ECO / ECN changes
  • Cost-down, lifecycle management
Series production
G6 · Post-launch reviewTargets met? Lessons learned
Gate / milestone (go · kill · hold · recycle)Model / protoTool samples (FOTS)
What you get from TDO: 2D & 3D drawingsResearch reportsTest reportsMeasurement reportsPrototypes